All Projects

Infrastructure

Gas Quality Project

Contract Type

Fixed Price

Location

Bacton Gas Terminal

Value

£1m

Architect

N/A

Timescale

18 months

Category

Infrastructure

Project Overview

Supporting the Principal Contractor with the installation of new fibreglass gas quality kiosks. Works included new concrete kiosk bases, new surface troughs, new buried ducts under roads, cable tray supports and the deconstruction of old kiosks as part of a project to increase the accuracy of monitoring the gas quality coming into the terminal.

Project Details

Contract Type Fixed Price
Location Bacton Gas Terminal
Value £1m
Architect N/A
Timescale 18 months
Category Infrastructure